Despite the cold weather over the past few weeks, progress continues across the railroad thanks to our dedicated Routen Tuten Workday leader. While most of us have been bundled up, work on the ramp track leading to the future shop has been moving full steam ahead.
Some refinements to the original design have been made, and John is once again doing what he does best. The updated plan narrows the ramp and adds a 20-foot level section near the top, creating a stable platform to improve safety and reduce loose rock and debris. Over the past several weekends, this new design has steadily taken shape as existing blocks were carefully removed and repositioned into their new layout.
To keep this momentum going, the next phase of work will involve relocating a switch and constructing a new switch off the passenger line to support the shop ramp. Be on the lookout for an upcoming workday announcement as we prepare for this important step. As always, thank you to everyone who continues to contribute their time, effort, and expertise.