The purpose of this project is to repair an area on the west loop near the Nicol bridge that needs about 40 feet of track repaired including moving a switch to a new location in order to provide better transition coming out of a curve heading towards the Nicol bridge. Because of the nature of this repair, it must be completed before our April 13th run day.
Proposed work schedule
Workday #1 (at any time before January 27th) - Identify and build track panel(s) need to be built as well as cut replacement ties that will be installed in numerous places in the area being repaired.
Workday #2 (Saturday, February 24th)- repairing and reworking west loop track section near Nicol bridge.
Workday #3 (Saturday, March 23rd) - All repair work must be completed by this date to make sure the railroad is operational again before our first public run day which is Saturday, April 13th.