Project 1: Clubhouse and Workshop Buildout

The purpose of this project is to take three 40ft shipping containers and combine them together to build out a clubhouse and workshop to use as a meeting space and shop. When completed the space will be about 960 square feet of usable space. The structure will have electricity, water, and climate control making the space useable year-round. In order to fully complete the build of the space a lot of work will need to be done along with raising the necessary funds to complete the building project. As of December 2023, it is estimated to cost between $10,000 and $13,000 to complete not including the hundreds of volunteer hours our membership and other volunteers will put in to complete. Below is an outline of workdays and tasks we are trying to complete during the work event.

Project 1:  Clubhouse & Shop Project

Workday 1 (Anytime between now and January 12, 2024) - Get the gravel pad cleaned up next to member container #3 so the blue container can be moved.  Once the gravel pad is ready, schedule to have the blue container moved.  Wes will make arrangements for a Bobcat to be available and Gene has agreed to operate the Bobcat.

 

When the blue container is moved, we also need to separate red container #1 from #2 so we can work on installing a center pier between container 1 & 2.

 

Workday 2 (Saturday, January 13, 2024):  Trench and pull electrical wire to shop container #1.  Depending on who is available we could also trench a water line from Breeseway to the shop container area.  Wes will arrange for a trencher and operator to be available for this workday.  We will need to mark the path of the trench ahead of this workday and call Georgia 811 to mark underground hazards.

 

Workday #3 (Saturday, February 10, 2024)- Since red containers 1 & 2 are separated we need to install center piers between container 1 & 2.  May also spend some time marking the cut lines for the inner walls between container 1 & 2.

 

Workday #4 (At any time before March 9, 2024) - The electrical panel should now be active. Some electrical work can be started in container 1.  Assumption is we may install some lights and outlets but all of that is to be determined.

 

Workday #5 (at any time before March 9, 2024) - Slide container 1 & 2 back together.  We will then schedule welding the roof line between container 1 & 2 together and mark the cut lines that will be used to cut out the inner wall between container 1 & 2 if those have not already been done.

 

Workday #6 (Saturday, March 9, 2024)- Cut out container 1 inner wall.  Not sure if we can do container #2 inner wall the same day.  I will assign a separate day for container #2 inner wall.  We may also want to work on sealing.

 

Workday #7 (at any time before Saturday, April 20th) - Mark cut lines in container #2 if not already completed.  If the inner wall in container 2 has already been removed, we will leverage this day for some other tasks for the shop.  One example could be to make sure the containers are watertight at the seam.  Other items will be determined prior to the Saturday, April 20th workday.

 

Workday #? (can be done anytime) - Install pier that will be leveraged between container 2 & 3. 

 

Workday #? (On Going) - Continue to build out container 1 & 2 to make the space functional before container 3 is installed.

 

We should also start considering some fundraising options to help fund the construction of the shop & club house.  Please start thinking of ideas that will help us raise the necessary funds to build out the shop & club house.  The current project workday list does not account for any track work that will need to be done in the future.

Previous
Previous

Project 2: West Loop track repair near the Nicol bridge

Next
Next

Meeting Minutes - October 7, 2023